A composting facility needs to be able to track material from the weighbridge to dispatch. A tunnel or windrow can perform well while the rest of the site backs up because difficult feedstocks build up at reception, curing space runs short or finished compost cannot be dispatched on time. The outline below is a starting point; the order of some sorting, storage and refining steps depends on the actual material flow. [1, 2, 5]

1. Intake: what comes in and where it goes

At intake, check the documents and source, weigh the delivery and inspect the load under the site's acceptance procedure. Record the apparent composition, foreign material and anomalies such as free liquid or an unusual odour. Assign the delivery an identifier that links it to each batch that receives it. Hold uncertain material separately only if the procedure allows it and the site has a suitable area. Otherwise, follow the rejection procedure without mixing it into accepted material. See feedstocks and contaminants. [2]

2. Store, sort and prepare the mix

Keep materials with different functions and risks apart. A buffer of clean wood chips can keep mixing on schedule; a wet, readily biodegradable delivery should not be held for the same length of time simply because there is room for it. If the feedstock is already compacted, check how long it was stored, how it was handled and when it can be blended. Remove foreign material as early as practicable, before size reduction makes it harder to separate. Shred to a particle size that allows even mixing without losing the structure needed for airflow. [1, 2, 3]

During preparation, record the mass and moisture content of each ingredient and check the structure of the resulting mix. The C:N ratio cannot tell you whether particles will compact under the weight of a windrow or whether wet pockets remain. Link the batch to the recipe actually used, including any recycled oversize, and check the mix in several places. See mix preparation. [1, 3]

3. Active composting and curing serve different purposes

During active composting, microorganisms consume oxygen and release heat. Depending on the technology, turning remixes the material and forced aeration moves air through the spaces between particles. Neither a running fan nor a single peak temperature tells you what is happening throughout the batch. Track temperatures over time at representative locations, alongside moisture and, where measured, gas concentrations within the material. Document sanitation using the procedure applicable to that material, including actual exposure rather than only the core temperature. [1, 2]

During curing, biological changes continue, usually releasing less heat than during the active stage. A cool but dry batch may simply be less active because of low moisture. Check its history, measurement conditions and indicators appropriate to the intended use before declaring it ready. Allow dedicated curing capacity, including room for batches that need longer. See compost maturity, stability and quality. [1, 4]

4. Refining, quality checks and dispatch

Screening separates fractions primarily by size. Only return the oversize fraction after screening as a bulking agent if it is suitable and clean enough for the purpose. Record contaminated rejects separately; recycling them brings impurities back into the mix. Keep batches awaiting test results separate from batches released for dispatch, and protect finished compost from recontamination from the intake area. Choose tests, particle size and dispatch conditions for the intended use and applicable requirements. [2, 3, 4]

5. Worked example: an intake rate of 10 t/day is not 10 t on site

For illustration, assume 10 t of prepared wet mix enters the active stage each day, seven days a week, with 21 days of active composting followed by 28 days of curing. First make two simplifying assumptions: mass stays constant and throughput is steady.

Table 1
StageSimplified calculationInventory at any one time
Active composting10 t/day × 21 days210 t
Curing10 t/day × 28 days280 t
Total for those two stages only210 t + 280 t490 t

If the measured average flow into curing is instead 8 t/day, the curing inventory would be about 224 t at 28 days, assuming no further mass loss during curing. This does not recalculate the active-stage inventory: that also depends on when mass is lost during the stage. Converting tonnes to volume requires the material's bulk density at that stage. The actual footprint also depends on pile geometry, manoeuvring space, seasonal peaks, intake and finished-product stock and equipment downtime. Neither the durations nor the mass loss in this example are design recommendations. [1, 5]

6. Where to look when material starts backing up

If stock builds up before the screen, compare daily tonnes transferred from curing with the amount actually screened, operating hours, days when material is too wet to screen and available space downstream. If finished compost is not being dispatched and is filling the refining area, a larger screen will not free up that space. Check water routes too: treat leachate from piles, run-off from working areas and clean stormwater as distinct streams in the design, with separate rules for collection and management. The same layout should identify equipment routes, water and power supplies, and the areas where air must be collected and treated if the installation requires it. [1, 2]

References and further reading

  1. NC State University Extension. Large-Scale Organic Materials Composting, “Composting Basics”, “Facility Siting and Development”, “Feedstocks” and “Testing”
  2. European Commission. Commission Implementing Decision (EU) 2018/1147, BAT 2, 19f and 33–36; technical reference for installations within its scope
  3. US EPA. Approaches to Composting, “Pile Structure” and “Pre-Processing Technologies”
  4. Oregon State University Extension. Interpreting compost analyses, selection of tests for intended use and indicators of stability
  5. International Compost Seminar 2026, Austria. 5 October (day 1), “Compost Facility Process Analysis”, PDF p. 3; 7 October (day 3), “Design of a Plant”, PDF p. 6. Organised by Compost Systems GmbH.